Question: 1 . A project involves eight activities as depicted in the figure below duration in days ) . Assume that the client has requested to
A project involves eight activities as depicted in the figure below duration in days Assume that the client has requested to complete the project in days.
Answer the following questions:
Identify the critical path for the project, and determine the earliest and latest times that the project can be completed.
Assume that Activity A actually finished on Day what is the total slack for Activity B now? If you were the project manager, what are the actions you would recommend in order to get the project back on schedule? Justify your answers.