Question: Determine the critical path for this set of data. Project Data begin{tabular}{|cccc} hline Activity & Duration & Predecessors hline 1 & A & 4

Determine the critical path for this set of data.
Project Data \begin{tabular}{|cccc} \hline Activity & Duration & Predecessors \\ \hline 1 & A & 4 & \\ \hline 2 & B & 6 & B \\ \hline 3 & C & 3 & A, B \\ \hline 4 & D & 6 & A \\ \hline 5 & F & 6 & A \\ \hline 6 & G & 10 & A, B \\ \hline 7 & H & 6 & C, E, G \\ \hline 8 & J & 10 & H \\ \hline 9 & J & 7 & C, F \\ \hline 10 & 4 & 2 & \end{tabular}