Question: The following table provides the predecessors and the three estimates of the duration of each activity. Activity Predecessors Duration Estimations Optimistic (a) Pessimistic (b) Most

The following table provides the predecessors and the three estimates of the duration of each activity.

Activity

Predecessors

Duration Estimations

Optimistic

(a)

Pessimistic

(b)

Most Likely

(m)

A- set up project

-

4

12

5

B- determine customer requirements

A

2

4

3

C- prepare SRS document

B

6

22

8

D- create test plans

C

4

8

6

E- implement system

C

3

5

4

F- developer testing

E

2

6

4

G- system testing

D, F

2

4

3

H- create user manuals

C

5

15

7

  1. Calculate expected activity durations of each activity
  2. Draw the PERT network diagram. Calculate earliest and latest starting and finishing times of each activity (apply forward and backward passes). For each activity, show all these calculations in a table. Table will look like

Early Start

Task Name

Early Finish

Slack Time

Late Start

Duration

Late Finish

  1. Determine the critical path and expected duration of the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!