Question: The following table provides the predecessors and the three estimates of the duration of each activity. Activity Predecessors Duration Estimations Optimistic (a) Pessimistic (b) Most
The following table provides the predecessors and the three estimates of the duration of each activity.
|
Activity |
Predecessors | Duration Estimations | ||
| Optimistic (a) | Pessimistic (b) | Most Likely (m) | ||
| A- set up project | - | 4 | 12 | 5 |
| B- determine customer requirements | A | 2 | 4 | 3 |
| C- prepare SRS document | B | 6 | 22 | 8 |
| D- create test plans | C | 4 | 8 | 6 |
| E- implement system | C | 3 | 5 | 4 |
| F- developer testing | E | 2 | 6 | 4 |
| G- system testing | D, F | 2 | 4 | 3 |
| H- create user manuals | C | 5 | 15 | 7 |
- Calculate expected activity durations of each activity
- Draw the PERT network diagram. Calculate earliest and latest starting and finishing times of each activity (apply forward and backward passes). For each activity, show all these calculations in a table. Table will look like
| Early Start | Task Name | Early Finish |
| Slack Time |
| |
| Late Start | Duration | Late Finish |
- Determine the critical path and expected duration of the project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock