Question: Determine the critical path. In your answer list all critical path activities. Calculate the total slack for each activity and list all activities and the

Determine the critical path. In your answer list all critical path activities.
Calculate the total slack for each activity and list all activities and the slack in your answer (example A,5)
What is the project duration for the network?
Is this network sensitive (why or why not).
(note: this answer will be manually graded by the instructor)
Activity Predecessor Duration (days)
A --1
B A 30
C A 60
D A 30
E D 20
F B 45
G C,F 95
H G 50
I E 50
J I 90
K H,J,L 75
L C 155
M K 120
N M 20