Question: Determine the critical path, total slacks for each activity and project duration for the network represented by the following table. Discuss the degree of sensitivity
Determine the critical path, total slacks for each activity and project duration for the network represented by the following table. Discuss the degree of sensitivity embodied by the network.
| Activity | Predecessor | Duration (days) |
| A | -- | 1 |
| B | A | 30 |
| C | A | 60 |
| D | A | 30 |
| E | D | 20 |
| F | B | 45 |
| G | C,F | 95 |
| H | G | 50 |
| I | E | 50 |
| J | I | 90 |
| K | H,J,L | 75 |
| L | C | 155 |
| M | K | 120 |
| N | M | 20 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
