Question: Determine the information missing from the table below, then answer the following question AVAILABLE WEEKS OF CRASHING CRASHING COST/WEEK ACTIVITY A B D E F

Determine the information missing from the table
Determine the information missing from the table below, then answer the following question AVAILABLE WEEKS OF CRASHING CRASHING COST/WEEK ACTIVITY A B D E F NORMAL TIME 4 3 4 5 4 1 CRASH TIME 2 2 4 3 1 1 NORMAL COST (5000) 8 9 10 10 11 6 CRASH COST (5000) 14 11 10 15 14 6 Which activity should be crashed fest for the project shown in the table above? Se OAD . . ODC OOG Cack to seed your answer -arch o