Question: determine the information missing from Tupelo then answer the following question if her decision is made to crash activity D in the table above by
determine the information missing from Tupelo then answer the following question
following question. B 3 D 5 A F + 4 NORMAL TIME NORMAL COST ($000s) 8 AVAILABLE WEEKS OF CRASHING CRASHING COSTI WEEK CRASH TIME 2 2 4 CRASH COST ($000s) 14 11 10 15 14 ACTIVITY A B D E 9 4 3 4 5 4 3 10 10 11 1 6 6
if her decision is made to crash activity D in the table above by one week what is the cost for this one week of crushing?
option A: $3,000
option B: $2,500
option C: $2,000
option D: this activity cannot be crashed
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock