Question: determine the minimum project cost which results when the project duration by is reduced by 3 days Consider the following project task information, where all
determine the minimum project cost which results when the project duration by is reduced by 3 days
Consider the following project task information, where all durations are give days arsts are given in de Activity Preceded Nominal Nominal by Duration Cost Crash Duration Crash Cost by Duration - 250 2 550 B - 3 200 1 600 750 1,350 500 650 DOO wa 1,300 1,900 DE 1800 1,800 L 400 2 450 the minimum project cost which results when the nrniert duratinnh