Question: Determine the project's duration if the time for activity C is 6 , for activity D is 5 , and for activity F is 2

Determine the project's duration if the time for activity C is 6, for activity D is 5, and for activity F is 2.
All activity times are in weeks.
table CPM
a.
14
b.
17
c.
16
d.
22