Question: Determine the project's duration if the time for activity C is 5 , for activity D is 8 , and for activity F is 6

Determine the project's duration if the time for activity C is 5, for activity D is 8, and for activity F is 6.
All activity times are in weeks.
Code
Prec.
Time
5
A -
7
?
D
B,
?
E
5
F
C, E
?
a.24
b.19
C.20
d: 17