Question: Use the following problem statement to answer questions 1 - 5 : The project network below shows setvi ty times fin weekl and their precedence
Use the following problem statement to answer questions : The project network below shows setvi ty times fin weekl and their precedence relationships.
What is the earliest start ES time for activity C
o
Question
pts
What is the latest finish LF time for activity
Question
pts
What is the estimated completion time of the project?