Question: Determines how many units the demand can be reached if the line starts with a cycle time of 30 minutes per unit and its learning
Determines how many units the demand can be reached if the line starts with a cycle time of 30 minutes per unit and its learning curve is based on 90%. The weekly demand is 500 pieces.The week has 5 days of two shifts of 450 minutes.
Step by Step Solution
There are 3 Steps involved in it