Question: Develop a Basic MOST analysis of the right-hand activities for the cable-clamp assembly shown in Figure (4.17) Right-Hand: Gets (G): Symbol: Time: Clamp (10) RE

  1. Develop a Basic MOST analysis of the right-hand activities for the cable-clamp assembly shown in Figure (4.17) Right-Hand:

Gets (G): Symbol: Time:

Clamp (10) RE G 1.00

First nut (9) RE G 1.00

Second nut (9) RE G 1.00

Place (P):

Cable clamp (10) M P RL 1.20

First nut (9) M P 1.20

Second nut (9) M P 1.20

Hold (H):

U-bolt (10) H 11.00

Run (R):

Down 1st nut U RL 3.40

Down 2nd nut U RL 3.40

Wait (W): UD 0.90