Question: Develop a Gantt chart for the activities in the table below and then answer the accompanying questions. Work breakdown Activity Expected Duration Predecessors Activity Expected
Develop a Gantt chart for the activities in the table below and then answer the accompanying questions. Work breakdown Activity Expected Duration Predecessors
| Activity | Expected Duration | Predecessors |
|---|---|---|
| A | 2 days | |
| B | 3 days | A |
| C | 4 days | A |
| D | 4 days | B, C |
| E | 5 days | B |
| F | 6 days | D |
| G | 4 days | C, E, F |
Identify all paths through the network. Which is the critical path?
Optional: Solve this problem with Microsoft Project. How does clicking on Tracking Gantt view demonstrate the critical path?