Question: Given the following information, answer the questions about this project: Activity Expected Duration Predecessors A 4 days B 9 days A C 11 days A
Given the following information, answer the questions about this project:
Activity | Expected Duration | Predecessors |
A | 4 days | |
B | 9 days | A |
C | 11 days | A |
D | 5 days | B |
E | 3 days | B |
F | 7 days | C |
G | 3 days | D, F |
H | 2 days | E, G |
I | 1 day | H |
- Draw the network as a Gantt chart.
- What is the critical path? Which activities have slack time?
- What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?