Question: Given the following information, answer the questions about this project: Activity Expected Duration Predecessors A 4 days B 9 days A C 11 days A

Given the following information, answer the questions about this project:

Activity

Expected Duration

Predecessors

A

4 days

B

9 days

A

C

11 days

A

D

5 days

B

E

3 days

B

F

7 days

C

G

3 days

D, F

H

2 days

E, G

I

1 day

H

  1. Draw the network as a Gantt chart.
  2. What is the critical path? Which activities have slack time?
  3. What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!