Question: Develop a logic network ( activity on node ) for the sequence of activities listed in the table below. Calculate and display ( in the

Develop a logic network (activity on node) for the sequence of activities listed in the table below. Calculate and display (in the node) the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), Total Float (TF), and Free Float (FF) for each activity. Also determine the Project Duration and identify (hi-lite) the Critical Path.
\table[[ACTIVITY,\table[[DURATION],[(days)]],PIB],[Start,0,None],[5,3,Start],[10,2,Start],[15,3,5],[20,4,5],[25,2,10],[30,3,15],[35,1,25],[40,4,20,30,35