Question: Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*. Period 1 2 3 4 5 6 7
Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table*.
| Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| Gross requirements | 30 | 40 | 40 | 70 | 20 | 10 | 70 | 60 |
*Holding cost = $1.50/unit/week; setup cost = $200; lead time = 1 week; beginning inventory = 40.
Develop a lot-for-lot solution (enter your responses as whole numbers).
| Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | |
| Gross requirements | 30 | 40 | 40 | 70 | 20 |
| 10 | 70 |
| ||||
| On-hand at beginning of period | 40 |
|
|
|
|
|
|
|
|
|
|
|
|
| On-hand at end of period |
|
|
|
|
|
|
|
|
|
|
| ||
| Order receipt |
|
|
|
|
|
|
|
|
|
| |||
| Order release |
|
|
|
|
|
|
|
|
|
|
|
Gross Requirements for Period 12 is 60.