Question: Develop a lot-for-lot solution of component X for the given gross requirements. It is the beginning of week 1 and there are currently 30 units

Develop a lot-for-lot solution of component X for the given gross requirements. It is the beginning of week 1 and there are currently 30 units of component X in stock. Component X has a lead time of 2 week. There are scheduled receipts planned for week 3 and week 4 of 20 each.

Develop a lot-for-lot solution of component X for

WILL GIVE THUMBS UP FOR CORRECT ANSWER!

Week 1 2 3 4 5 Gross requirements (start of period) 100 500 Schedule receipts (start of period) Projected on hand (start of period) Net requirements Planned order receipts Planned order releases