Question: Develop a material requirements plan for item P and its components, given the tree below. Assume that all lead times are one week, and that
Develop a material requirements plan for item and its components, given the tree below. Assume that all lead times are one week, and that lotforlot ordering is used except for item F which is ordered in multiples of units.
One hundred units of are needed at the start of each of weeks and
Beginning inventories are: and Scheduled receipts are: at the start of week