Question: Develop a network ( Critical Path Method, CPM ) You have signed to build a garage for a small company. The expected times for the

Develop a network (Critical Path Method, CPM)
You have signed to build a garage for a small company. The expected times for the project activities are given below.
ID
Description
Predecessor
Time (days)
A
Pour foundation
None
3
B
Put frame
A
4
C
Roof
B
5
D
Windows
B
1
E
Doors
B
1
F
Electrical
B, E
3
G
Rough-in-frame
C, D, E
2
H
Door opener
E, F
1
I
Paint
G, H
2
J
Release
I
1
Find the critical path?
Find the expected project completion time?
The critical path: A B E H I J
The project completion time: 21 days
The critical path: A B C G I J
The project completion time: 17 days
The critical path: A B D G I J
The project completion time: 17 days
The critical path: A B F G I J
The project completion time: 18 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!