Question: Develop a network ( Critical Path Method, CPM ) You have signed to build a garage for a small company. The expected times for the
Develop a network Critical Path Method, CPM
You have signed to build a garage for a small company. The expected times for the project activities are given below.
ID
Description
Predecessor
Time days
A
Pour foundation
None
B
Put frame
A
C
Roof
B
D
Windows
B
E
Doors
B
F
Electrical
B E
G
Roughinframe
C D E
H
Door opener
E F
I
Paint
G H
J
Release
I
Find the critical path?
Find the expected project completion time?
The critical path: A B E H I J
The project completion time: days
The critical path: A B C G I J
The project completion time: days
The critical path: A B D G I J
The project completion time: days
The critical path: A B F G I J
The project completion time: days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock