Question: Develop a network diagram and analyze the network to obtain the critical path as well as the project duration. Question - 3: 25 Points Prepare

 Develop a network diagram and analyze the network to obtain the

Develop a network diagram and analyze the network to obtain the critical path as well as the project duration. Question - 3: 25 Points Prepare an Early Start Schedule for the network shown. Indicate the allowable time span for each activity. Activity durations are in days