Question: Develop a resource constrained schedule for the below project activities based on the following resource requirements and the resource constraint condition i.e. not more than

Develop a resource constrained schedule for the below project activities based on the following resource requirements and the resource constraint condition i.e. not more than 6 resources available each day (30 marks)Develop a resource constrained schedule for the

Activity Predecessor Activity Resource Requirements a 3 a b d || b 2 Duration 5 days 7 4 6 9 6 4 6 8 9 10 9 3 a b b d, e d, e f, g, h i f g h i j k 1 d 2 CD 1 f 2 g 3 h 2 3 j 2 k 1 1 3