Question: Question 2: Based on the below project schedule, (i) Develop the project Network diagram (10 marks), Identify the Critical Path and Total duration of the

Question 2: Based on the below project schedule,Question 2: Based on the below project schedule,

Question 2: Based on the below project schedule, (i) Develop the project Network diagram (10 marks), Identify the Critical Path and Total duration of the project (10 marks) and Find each activity's ES, EF, LS and LF and determine which activities has free slack (10 marks) (iii) Activity Duration Predecessor a b d 4 6 4. 2 4 5 3 4 2 None a a b b, d e f W g h i f, g e, h Question 3: Develop resource constrained schedule for the above project in Question 2 based on the below resource requirements and the resource constraint condition i.e. not more than 4 resources available per day (15 marks) Activity Resource Requirements a 3 b 2 3 d 2 e 3 f 2 g 3 h 2 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!