Question: Develop a resource schedule based on the scheduled activites provided. . Use the parallel method and follow the heuristics rules. Be sure to update each
Develop a resource schedule based on the scheduled activites provided. . Use the parallel method and follow the heuristics rules. Be sure to update each period. For this project there is only three (3) resources available for each time period for the entire duration of the project.
| ID | Dur | Resource Required |
| 1 | 1 | 1 |
| 2 | 3 | 2 |
| 3 | 4 | 2 |
| 4 | 5 | 1 |
| 5 | 4 | 2 |
| 6 | 2 | 2 |
a) List the order in which you scheduled ALL activites of the project based on the resource constraint.
b) Based on the recomputed schedule from part A, list ALL activities and its new slack time.
c) What is the expected length of the project based on the resource constraint.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
