Question: Develop a resource schedule based on the scheduled activites provided. . Use the parallel method and follow the heuristics rules. Be sure to update each

Develop a resource schedule based on the scheduled activites provided. . Use the parallel method and follow the heuristics rules. Be sure to update each period. For this project there is only three (3) resources available for each time period for the entire duration of the project.

ID Dur

Resource

Required

1 1 1
2 3 2
3 4 2
4 5 1
5 4 2
6 2 2

a) List the order in which you scheduled ALL activites of the project based on the resource constraint.

b) Based on the recomputed schedule from part A, list ALL activities and its new slack time.

c) What is the expected length of the project based on the resource constraint.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!