Question: Develop a resource schedule for the project network below, which requires a team of programmers for its development. However, only 5 programmers are available. Activity
Develop a resource schedule for the project network below, which requires a team of programmers for its development. However, only programmers are available.
Activity Subtitle
tableESIDEFSLACKRESOURCE,SLACKLSDURATION,LF
Use the parallel method and the following heuristics to develop a schedule for the project: Shortest slack. Shortest duration. Smallest identification number.
a Present the project's workload. Report eventual resource overallocations. point
b Present a new workload for the project. What is the new critical path and project duration after rescheduling the resources? point