Question: Normal No Spacing Heading AaBbCcDdE AaBbs Title Develop a resource schedule for the project network below, which requires a team of programmers for its development.
Normal
No Spacing
Heading
AaBbCcDdE
AaBbs
Title
Develop a resource schedule for the project network below, which requires a team of programmers for its development. However, only programmers are available.
Use the parallel method and the following heuristics to develop a schedule for the projecti. Shortest slack, Shortest duration, Smallest identification number.
a Present the project's workload, Report eventual resource overallocations. point
b Present a new workload for the project, What is the new critical path and project duration after rescheduling the resources? point
ORIGINAL LOAD CHART
DURATION:
CRITICAL PATH:
RESCHEDULED LOAD CHART
tableIDRES.,DUR.,ESLFSLACK,TOTAL RESOURCES,RESOURCES AVAILABLE,
DURATION:
CRITICAL PATH:
Normal
No Spacing
Heading
AaBbCcDdE
AaBbs
Title
Develop a resource schedule for the project network below, which requires a team of programmers for its development. However, only programmers are available.
Use the parallel method and the following heuristics to develop a schedule for the projecti. Shortest slack, Shortest duration, Smallest identification number.
a Present the project's workload, Report eventual resource overallocations. point
b Present a new workload for the project, What is the new critical path and project duration after rescheduling the resources? point
ORIGINAL LOAD CHART
DURATION:
CRITICAL PATH:
RESCHEDULED LOAD CHART
tableIDRES.,DUR.,ESLFSLACK,TOTAL RESOURCES,RESOURCES AVAILABLE,
DURATION:
CRITICAL PATH:
Normal
No Spacing
Heading
AaBbCcDdE
AaBbs
Title
Develop a resource schedule for the project network below, which requires a team of programmers for its development. However, only programmers are available.
Use the parallel method and the following heuristics to develop a schedule for the projecti. Shortest slack, Shortest duration, Smallest identification number.
a Present the project's workload, Report eventual resource overallocations. point
b Present a new workload for the project, What is the new critical path and project duration after rescheduling the resources? point
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock