Question: Develop a resource schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the

Develop a resource schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Note: activities 2, 3, 5, and 6 use two of the resource skills. Three of the resource skills are available. How has slack changed for each activity? Has the risk of being late changed? How?