Question: Develop a resource schedule using as your template the loading chart below. Use the parallel method and heuristics given. Be sure to update each period
Develop a resource schedule using as your template the loading chart below. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Note: activities use the resource skills as shown in the network diagram. Four of the resource skills are available.
Note: Recall, in the schedule resource load chart the time-constrained scheduling interval (ES through LF) has been shaded. Any resource scheduled beyond the shaded area will delay the project. "TP" stands for time period.
Recompute your slack for each activity given your new schedule.
What is the slack for Activity 1, Activity 4, and Activity 5?