Question: Develop a resource-constrained schedule in the loading chart given in Appendix A. Use the parallel method and follow the heuristics; minimum slack, smallest duration, lowest

Develop a resource-constrained schedule in the loading chart given in Appendix
A. Use the parallel method and follow the heuristics; minimum slack, smallest
duration, lowest identification number. Fill in the early start (ES), late finish (LF)
and slack (SL) for the new schedule and highlight the slack in the table
b) You are assigned to manage six (6) Engineers that are expert in your project. Activities A and D require 3 Engineer at one time to complete while activities B, C, E and Frequire 4 Engineers Table 2 Activity List Activity Predecessor Duration Requirement (Engineer) A 8 2 B 10 4 8 4 D A,B 10 2 E B 6 4 F C,D,E 4 1) Draw the Network Diagram for your project and find the critical path. (5 marks) ii) Develop a resource-constrained schedule in the loading chart given in Appendix A. Use the parallel method and follow the heuristics; minimum slack, smallest duration, lowest identification number. Fill in the early start (ES), late finish (LF) and slack (SL) for the new schedule and highlight the slack in the table. (15 marks)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
