Question: Develop a solution for the following line balancing problem. Allowing a cycle time of 4 minutes, design a NEW process using the most following task

Develop a solution for the following line balancing problem. Allowing a cycle time of 4 minutes, design a NEW process using "the most following task" heuristic approach. Mark the correct answer Workstation 1: (A,R); Workstation 2: (S) Workstation 1: (A,B,N); Workstation 2: (T,R); Workstation 3: (K), Workstation 4: (s) Workstation 1: (A,B,N); Workstation 2: (K); Workstation 3: (S) Workstation 1: (T); Workstation 2: (K); Workstation 3: (S)