Question: Develop a solution for the following project problem. Act Pred. Normal Time (Weeks) Crash Time Normal Cost Crash Cost (total) Crash cost per (week) A
Develop a solution for the following project problem.
Act | Pred. | Normal Time (Weeks) | Crash Time | Normal Cost | Crash Cost (total) | Crash cost per (week) |
A | - | 6 | 5 | $900 | $1000 |
|
B | - | 8 | 6 | $300 | $400 |
|
C | - | 4 | 3 | $500 | $600 |
|
D | A | 5 | 3 | $900 | $1200 |
|
E | C | 8 | 5 | $1000 | $1600 |
|
d) Find the new total cost of completing the project (after crashing).