Question: Example 2 . 3 4 The utility data for a network is given in Table 2 . 1 1 1 . Crash the network to

Example 2.34
The utility data for a network is given in Table 2.111. Crash the network to minimum possible duration and find the associated cost. The total normal cost of the project is `9,00,000.
Table 2.111 Project activity details
Activity Normal Time (Weeks) Crash Time (Weeks) Cost Slope (`000)
12427
13744
23743
245312
35636
45418
4610610
5666--
578610
686412
78527
Note: The indirect cost is not given, and hence, the optimal project duration and associated optimal
cost cannot be found.
Solution:
Minimum project duration is 19 days and the total cost for crashing up to 19 weeks is `10,74,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!