Question: Develop MRP for component E. Lead times for all items are two weeks. 100 units of A are needed at the start of week 10.
Develop MRP for component E. Lead times for all items are two weeks. 100 units of A are needed at the start of week 10. There are currently 20 units of B and 130 of E on hand, and 50 units of E are in production and will be completed by the start of week 2. Lot-for-lot ordering is used for all items.