Question: Develop the activity sequence model and determine the normal time for the following work activities A worker walk 4 steps, goes through a door and
Develop the activity sequence model and determine the normal time for the following work activities
- A worker walk 4 steps, goes through a door and walk 6 steps and grasp light piece of wood.
- He moves 6 steps to drilling machine and place with adjustment the piece of wood in the machine.
- He presses the button to make the machine start and it takes 28 sec to drill all the holes.
- He grasps the piece of wood after drilling and moves to the table which is 9 steps away and set on the chair and place it on the table.
- he collects 4 screws from the pin next to him and place each screw inside the hole and it require light pressure to do so.
- he grasps the screw driver near him and turn each screw 5 turns using wrist action. After that, he put aside the screw driver and standup and return to the drilling machine
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock