Question: Develop the critical chain for the following: Project Design Production Training Deadline Penalty A 4 weeks 8 weeks 4 weeks Week 20 $50K/week B 8
Develop the critical chain for the following:
| Project | Design | Production | Training | Deadline | Penalty |
| A | 4 weeks | 8 weeks | 4 weeks | Week 20 | $50K/week |
| B | 8 weeks | 12 weeks | 4 week | Week 25 | $30K/week |
Given the due dates and penalties, schedule A activities before B, using one design crew, one production crew, and one training crew.Show each step of the critical chain analysis.