Question: Develop the material requirements plan for component H of the end product A that has the following product structure tree. Lead times for A and
Develop the material requirements plan for component H of the end product A that has the following product structure tree. Lead times for A and each component except B are one week. The lead time for B is three weeks. Fify units of A are needed at the start of week 8 . There are currently 20 units of B and 105 units of E Projected on hand, and 40 units of H are in production by a supplier and are scheduled to be received by the start of week 2. (Do not leave any empty spacest ingut a 0 wherever it is required.)