Question: DEVELOPING A PRECEDENCE DIAGRAM FOR AN ASSEMBLY LINE Boeing wants to develop a precedence diagram for an electrostatic wing component that requires a total assembly

DEVELOPING A PRECEDENCE DIAGRAM FOR AN ASSEMBLY LINE
Boeing wants to develop a precedence diagram for an electrostatic wing component that requires a total assembly time of 65 minutes.
APPROACH Staff gather tasks, assembly times, and sequence requirements for the component in Table 9.2.
TABLE 9.2
Precedence Data for Wing Component
\table[[TASK,\table[[ASSEMBLY TIME],[(MINUTES)]],\table[[TASK MUST FOLLOW TASK],[LISTED BELOW]],],[A,10,-,\table[[This means that tasks B
 DEVELOPING A PRECEDENCE DIAGRAM FOR AN ASSEMBLY LINE Boeing wants to