Question: Devise an SPT SCHEDULE FOR THE AUTOMATIC ROUTING MACHINE, the requirement is a. average job flow time b. average hours early c. average hours past

Devise an SPT SCHEDULE FOR THE AUTOMATIC ROUTING MACHINE, the requirement is
a. average job flow time
b. average hours early
c. average hours past due
d. average WIP
e. average total inventory
thank you will vote, just dont understand how Devise an SPT SCHEDULE FOR THE AUTOMATIC ROUTING
Order Processing Time (hr) AZ135 14 Due Date (hrs from now) 14 DM246 8 20 SX435 10 6 PC088 3 18