Question: Order Processing Time (hr) Due Date (hrs from now) AZ135 14 14 DM246 8 20 SX435 10 6 PC088 3 18 a) Average job flow
| Order | Processing Time (hr) | Due Date (hrs from now) |
| AZ135 | 14 | 14 |
| DM246 | 8 | 20 |
| SX435 | 10 | 6 |
| PC088 | 3 | 18 |
a) Average job flow time
b) Average hours early
c) Average hours past due
d) Average WIP
e) Average total inventory
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts