Question: DiagramDescription automatically generated What is the earliest that Activity D can begin if Activity A takes 3 days, Activity B takes 5 days, and Activity

DiagramDescription automatically generated
What is the earliest that Activity D can begin if Activity A takes 3 days, Activity B takes 5 days, and Activity C takes 7 days?
Question 52Select one:
a.
Day 15
b.
Day 5
c.
Day 7
d.
Day 3