Question: Diane is the project manager for a three-year project to retrofit a pre-war building for LEED Silver Certification. After six months, the project is significantly
Diane is the project manager for a three-year project to retrofit a pre-war building for LEED Silver Certification. After six months, the project is significantly behind schedule and over budget. The team realizes that they did not fully understand all the requirements for the certification, so the basis of estimates was not valid. Diane will now forecast the estimate at completion (EAC). Based on the following information about the project, what is the EAC? BAC = $600 Million Bottom-up ETC (Months 7 to 36) = $ 575 CPI = 0.8 SPI = 0.7 (For Ref Only, Question #: PM-02568) Group of answer choices $750 M $617.5 M $675 M $662.5 M