Question: Dinners are prepared in a process with two sequential resources. The capacities of the resources are 6 . 2 and 6 . 9 dinners per

Dinners are prepared in a process with two sequential resources. The capacities of the resources are 6.2 and 6.9 dinners per hour.
What is the capacity of this process in terms of dinners per hour?
Note: Round your answer to 3 decimal places.