Question: Dinners are prepared in a process with two sequential resources. The capacities of the resources are 30 and 43 dinners per hour. Instruction: Round your

Dinners are prepared in a process with two

Dinners are prepared in a process with two sequential resources. The capacities of the resources are 30 and 43 dinners per hour. Instruction: Round your answer to three decimal places. What is the capacity of this process in terms of dinners per hour? dinners per hour