Question: Dipesh is the project manager and trying to estimate the cost of an activity. in the optimistic scenario he thinks the activity is expected to

Dipesh is the project manager and trying to estimate the cost of an activity. in the optimistic scenario he thinks the activity is expected to cost only $6,000, in the pessimistic scenario this number is $24,000 and the most likely case number is $18,000. What is the expected activity cost (use three-point estimation (beta)?0$1)17,0000$
2)15,0000$
3)18,000 $
4)24,000