Question: Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct

Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis

Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 70,000 units of product were as follows:

Standard Costs Actual Costs
Direct materials 182,000 lbs. at $5.60 180,200 lbs. at $5.50
Direct labor 17,500 hrs. at $16.10 17,900 hrs. at $16.40
Factory overhead Rates per direct labor hr.,
based on 100% of normal
capacity of 18,260 direct
labor hrs.:
Variable cost, $4.60 $79,700 variable cost
Fixed cost, $7.30 $133,298 fixed cost

Each unit requires 0.25 hour of direct labor.

Required:

a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct Material Price Variance $fill in the blank 1

FavorableUnfavorable

Direct Materials Quantity Variance $fill in the blank 3

FavorableUnfavorable

Total Direct Materials Cost Variance $fill in the blank 5

FavorableUnfavorable

b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct Labor Rate Variance $fill in the blank 7

FavorableUnfavorable

Direct Labor Time Variance $fill in the blank 9

FavorableUnfavorable

Total Direct Labor Cost Variance $fill in the blank 11

FavorableUnfavorable

c. Determine variable factory overhead controllable variance, the fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Variable factory overhead controllable variance $fill in the blank 13

FavorableUnfavorable

Fixed factory overhead volume variance $fill in the blank 15

FavorableUnfavorable

Total factory overhead cost variance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!