Question: Discussion Number 1. Discuss Project crashing. Using the following example show how calculations are made to know which activity to crash. Example Activity I. D
Discussion Number 1. Discuss Project crashing. Using the following example show how calculations are made to know which activity to crash. Example Activity I. D Slope Maximum crash time Direct Costs Normal Crash Time Cost Time Cost A $ 30 3 5 $ 60 2 $ 150 B 20 2 7 30 5 70 C 40 1 6 40 5 80 D 25 4 10 25 6 125 E 50 2 8 70 6 170 F 0 0 6 30 6 180 Note the activity Sequences are: A - B - D - F A - C - E - F The Indirect costs are : A = 350 B = 300 C = 275 D = 200 E = 175 F = 150