Question: Discuss Project crashing. Using the following example show how calculations are made to know which activity to crash. Example Activity I. D Slope Maximum crash
Discuss Project crashing. Using the following example show how calculations are made to know which activity to crash.
Example
| Activity I. D | Slope | Maximum crash time | Direct Costs | |||
| Normal | Crash | |||||
| Time | Cost | Time | Cost | |||
| A | $ 30 | 3 | 5 | $ 60 | 2 | $ 150 |
| B | 20 | 2 | 7 | 30 | 5 | 70 |
| C | 40 | 1 | 6 | 40 | 5 | 80 |
| D | 25 | 4 | 10 | 25 | 6 | 125 |
| E | 50 | 2 | 8 | 70 | 6 | 170 |
| F | 0 | 0 | 6 | 30 | 6 | 180 |
Note the activity Sequences are:
A - B - D - F
A - C - E - F
The Indirect costs are :
A = 350
B = 300
C = 275
D = 200
E = 175
F = 150
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
