Question: Discuss Project crashing. Using the following example show how calculations are made to know which activity to crash. Example Activity I. D Slope Maximum crash

Discuss Project crashing. Using the following example show how calculations are made to know which activity to crash.

Example

Activity I. D

Slope

Maximum crash time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

$ 30

3

5

$ 60

2

$ 150

B

20

2

7

30

5

70

C

40

1

6

40

5

80

D

25

4

10

25

6

125

E

50

2

8

70

6

170

F

0

0

6

30

6

180

Note the activity Sequences are:

A - B - D - F

A - C - E - F

The Indirect costs are :

A = 350

B = 300

C = 275

D = 200

E = 175

F = 150

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!