Question: Do a GANTT Chart based on the Activities listed below (10 points answer in an Excel or Word format): Activity A. Operating Room (OR)
Do a GANTT Chart based on the Activities listed below (10 points answer in an Excel or Word format): Activity A. Operating Room (OR) Design B. Doctors' input C. Review Design D. Final Approval by Doctors E. Permits F. Getting quotes G. OR Manuals H. Order & Install equipment I. Train personnel on manuals J. Get OR up and running Duration 2 months 2 months 1 month 1 month 1 month 2 1 month 2 1 month 1 month months months Prerequisite None A A, B C I, H Q2: How long is the duration of this project? (2 points) Q3: Can you do "Getting Quotes" before "Permits" are completed? (2 points) Q4: Can you Train Personnel on Manuals before you Order & Install Equipment? (2 points)
Step by Step Solution
3.39 Rating (155 Votes )
There are 3 Steps involved in it
Q1 A C D G I J 5 weeks Q2 Yes you can do Getting Quates before Permits ... View full answer