Question: do b, c, d please 2 pts a) Calculate the length & variance of the critical path. 3 pts b) What is the approximate probability

do b, c, d please
do b, c, d please 2 pts a) Calculate the length &
2 pts a) Calculate the length & variance of the critical path. 3 pts b) What is the approximate probability that the jobs on the CP will be completed in 41 days? 3 pts c) What is the approximate probability that the jobs on the next most CP will be completed in 41 days? 2 pts d) What is the probability that the entire project will be completed in 41 days